A guarantor had been suspended. He filed for preliminary relief, and everyone watched the lawsuit with bated breath. After all, this was finally going to yield a ruling on the quality of guarantees. But nothing could be further from the truth, and the uncertainty continues.
The judge’s ruling left nothing to be desired in terms of clarity. The suspension must be lifted, and Borger BK must regain access to Apexion’s quality assurance tool. That’s great news for the affected parties whose projects had come to a standstill. But this preliminary injunction still leaves a bad taste in the mouth. We haven’t made any progress at all.
During the hearing, it became clear that the judge wasn’t at all interested in what exactly matters to builders and guarantors. In the ruling, it essentially came down to simply determining whether or not the procedures had been followed.
Instrument provider Apexion had initially issued a warning to guarantor BK, but later withdrew it to give BK the benefit of the doubt. Nevertheless, they had used the suspension period that corresponded to that original warning. And you simply can’t retract a warning only to then use that same warning as the basis for imposing a suspension after all. So the case was simple enough. Just swallow that suspension. And do it quickly.
To the judge, everything else that was discussed was just a smokescreen. But it was also striking that virtually everything discussed revolved around procedures. How should the evidence be entered into the system? Does it have to be done directly, or can you use your own software for that? That was up for debate. The suspicion of poor governance was briefly raised by Flip van der Linden, technical director of the system provider Apexion. He had conducted a comprehensive data analysis. But in the end, he was unable to prove that the flaws revealed by the analysis had nothing to do with the poor integration of the various software components. And so he was unable to substantiate his claim that the citizen’s software was “cheating software.”
So the only clarity this case provided was that the Wkb is still experiencing teething problems. And that comes as no surprise to very few people.
The painful conclusion is that the Wkb has once again been left looking foolish. There was great anticipation surrounding the case, but all we’ve seen is some squabbling over procedures that apparently have been fluid all along. Yet that squabbling has, in the meantime, brought 1,200 construction projects to a standstill for months. Through no fault of the people who were building their homes. That suffering was also mentioned in the courtroom, but it was legally irrelevant as well.
That is why it has become particularly clear that very effective and flexible procedures must be put in place to prevent this kind of collateral damage.
And pretty quickly, too.